Here is the agenda provided by the committee:

1. Call to Order

2. Approval of Minutes April 23, 2024

3. Public Comment – 10 minutes per topic

4. Director’s Report

a. Watermain Breaks: 18 YTD

b. CIP Projects Update

i. 2022 Sewer Rehabilitation

1. Request final payment approval to National Power Rodding Corp. for the remaining five percent retainage for the 2022 Sewer Rehabilitation Program in the amount of $19,921.21-Agenda

ii. 2024 Sewer Rehabilitation Program

1. Request approval to award the 2024 Sewer Rehabilitation Program to National Power Rodding Corp. for their lowest bid in the amount of $441,225.00-Agenda

iii. 80th Ave Pump Station

1. Request payment approval to Garland/DBS, Inc for the replacement roof at the 80th Ave Pump Station in the amount not to exceed $72,485.00-Agenda

c. Public Works Soil Disposal

i. Request payment approval to Groen Transfer an Allied Waste Company DBA: Republic Services for the disposal of 503.70 tons of soil in the amount of $25,185.00-Agenda

d. Request approval for conducting a Fire Hydrant Maintenance and Flow/Watermain Capacity Testing program with M.E. Simpson Co., Inc in the amount of $18,810.00-Agenda

e. Request approval for conducting a Water Distribution System Valve Exercising program with M.E. Simpson Co., Inc in the amount of $21,942.00-Agenda

5. 12858 Forestview Road

6. Professional Services

a. Request approval of Construction Engineering Services with Lockwood, Andrews, & Newnam, Inc. for the 70th Ave Lift Station Rehabilitation in the amount not to exceed $46,560.00-Agenda

b. Request approval for conducting a Water Distribution System Leak Detection program with M.E. Simpson Co., Inc in the amount of $20,000.00-Agenda

c. Request payment approval for professional engineering services with RJN Group for the 2023 & 2024 Sewer Rehabilitation Design and Construction, On-Call Underground Infrastructure Services, 2024 CCTV & MH Inspections rendering through May 31, 2024 in the amount of $4,055.00- Agenda

7. Old Business

8. New Business

9. Motion to Adjourn

https://palosheights.org/AgendaCenter/ViewFile/Agenda/_06252024-1023